IDC Municipal Nano-Grid
Green Energy Funding Proposal
IDC Nano-Grid
Municipal Nano-Grid Deployment Programme
A strategic initiative to deploy 3kWp Solar PV and 10kWh Battery Energy Storage Systems across four South African municipalities, achieving NERSA-compliant sustainable electricity trading status.
4
Total Municipalities
Northern & Eastern Cape Regions
18,553
Households Served
Direct beneficiaries
R1.34B
Total Funding Required
20-year infrastructure loan
42%
Cost Avoidance
Annual savings vs Eskom
UtCS has been appointed as the strategic implementation partner to assist the participating municipalities in achieving NERSA-defined Sustainable Electricity Trading Status. This status requires municipalities to achieve an Electricity Price Margin (EPM) of minimum 60% after settling Bulk Supply Costs.
Strategic Objective
Deploy innovatively and strategically placed Nano-Grids to impose maximum cost avoidance, enabling municipalities to achieve the 60% EPM benchmark.
Financial Impact
Through TOU arbitrage and maximum demand reduction, achieve >40% total cost avoidance, directly improving each municipality's financial sustainability.
| Performance Indicator | Benchmark | Acceptable Range |
|---|---|---|
| Electricity Price Margin (%) | 60% | 58% - 62% |
| Bulk Purchase Cost / Total Expenditure (%) | 75% | 58% - 78% |
| Energy Losses (%) | 10% | 5% - 12% |
| Revenue Collection Rate (%) | 95% | 95% |
| Repairs & Maintenance (% of revenue) | 6% | 6% - 15% |
| Net Surplus Margin (%) | 15% | 10% - 20% |
Source: NERSA Guidelines - Municipalities that operate within these benchmarks are expected to run a sustainable and efficient electricity business.
| Municipality | Households | Funding Required | Annual Eskom Cost | Cost Avoided | Reduction |
|---|---|---|---|---|---|
| Dr Beyers Naude | 12,644 | R910.37M | R152.13M | R88.24M | 42% |
| Hantam | 2,879 | R207.29M | R30.18M | R17.51M | 42% |
| Richtersveld | 2,095 | R150.84M | R20.20M | R11.72M | 42% |
| Kamiesberg | 935 | R67.32M | R15.82M | R9.17M | 42% |
| Total Programme | 18,553 | R1.34B | R218.34M | R126.63M | 42% |
Total Investment Opportunity
R 1 335 816 000
Combined Nano-Grid deployment cost across all 4 municipalities
PV Cost Component
R742.13M
BESS Cost Component
R890.54M